Phase three > Construction Details > Comprehensive details
In this section we have prepared some Information about duration of some important construction activities of the first 25 Floors Tower, located in the third phase.
In the near future we will also provide the cost analysis for the different stages.
Row |
Activity |
Start Date |
Finish Date |
1 |
Pile Excavations ,piles Armature baskets and piling |
15/04/2008 |
27/08/2008 |
2 |
Cleaning & casting meagre concrete in Foundation |
15/06/2008 |
13/11/2008 |
3 |
Distribution of bars |
31/08/2008 |
22/02/2009 |
4 |
Mounting Temporary base plates |
10/11/2008 |
11/03/2009 |
5 |
Foundation Casting Concrete |
25/02/2009 |
3/05/2009 |
6 |
Temporary Bridge |
29/06/2008 |
01/09/2008 |
7 |
Factory for Steel Structure |
09/05/2009 |
15/12/2009 |
8 |
Steel Structure |
04/08/2009 |
continued.. |